The 1.80 m wide bracket requires only a minimum of space and provides an inexpensive alternative to the SKSF 240. Eelised • Stable and cost-effective for high loads Generous bracket spacings allow large-area formwork units with optimal utilization of the bearing capacity. This leads to extremely economical solutions. • Economical and safe anchoring The M30/DW20 and M36/DW26 climbing cones have been designed especially for single- sided concreting using SKS/SSC in dam construction, and to allow the transfer of high tensile and shear forces into the still fresh, unreinforced concrete. The corrosion-protected cones can be re-used – only the tie rods and threaded anchor plates remain in the concrete. • Simple and flexible planning With PERI SKSF 240 and SKS 180 single-sided climbing formwork, circular structures can also be concreted without undergoing any large planning process. Even use on inclined
made available to all work crews on the job site, and they made extensive use of it, coming to the office view it from time to time to explore the finer details of positioning of formwork, cable anchors and reinforcement. For example, as can be seen in figure 9.8.7, the cable anchors are heavy and they have to be supported before casting. Large quantities of reinforcement were positioned next to the cable anchor. Planning how to support the cable anchor within the forms in preparation for concreting was much easier with the 3D view, which could be manipulated and cross-sectioned in multiple directions. 104 Fig. 9.8.7 Cut section views showing reinforcement details in relation to other cast-in hardware, such as the large cable anchor assemblies. 9.8.4.2 Design and planning of temporary structures and clash detection.