Kuidas muudab mudelprojekteerimine teraskonstruktsioonide valmistamist ja ehitamist
you are going to do it… it was more of a sequence of events, but the days and durations
were not inserted in there, other than we gave them an overall duration to erect the
building and said that here is the sequence you need to do it in.
13. Were BIM models used for site planning (e.g. cranes)? If yes, please describe.
No, that was pretty much done on 2D drawings – figuring out what is your overall
hoisting range, we used the SK400 tower crane on the job. We pretty much figured out
where we have to plant that so we could get it out at some point, and where is it going to
reach.
14. Did you experience a reduction in RFIs & change orders & construction time, compared to
projects of similar complexity?
Maybe… there were a lot of RFI’s on that job, after decisions were made in reviewing
things in the 3D model, we confirmed that in a RFI. We still used the RFI at the end of