Kuidas muudab mudelprojekteerimine teraskonstruktsioonide valmistamist ja ehitamist
Due to the fact that almost every subcontractor had to submit a 3D model to the general
contractor for review, a comprehensive cash detection was possible. For example, where
the HVAC ductwork clashed with a steel beam, an opening was indicated in the model.
Because all the ventilation ductwork was hidden in the confined space of the sloping
walls, it was important to discover all the clashes during the design phase. This way the
structural engineer had enough time to reanalyze the modified beams and make necessary
adjustments. Additionally, BIM tools allowed to speed up the shop drawing review
process, by viewing the model remotely in Tekla during online meetings. Critical steel
members were modeled with alignment control holes to hold a surveyor’s prism. Their
46
position was indicated in the BIM model in the form of XYZ coordinates, which were