While imposing the penalty to the li-
censee the timeframe and relevant terms of fulfillment of the terms of license shall be determined.
4. If, despite the imposed liability provided by this Article, the terms of license is not fulfilled
by the licensee the licensor shall make the decision on cancellation of the license.
Article 26. General rule of issuing a permit
2. A building permit shall be granted and the related administrative procedures shall be ac-
complished in 60 days. The rule and the terms of issuance (including simplified issuance) of a
building permit are regulated by the normative act of the Government of Georgia.
10. The permit issuer is obligated to make a decision on issuance of a permit in 20 days from
submission of the application. If the decision on issuance of the permit or refusal it is not made
in the said time the permit shall be considered issued.
Article 261