Integration of Lean Con. and Building Information Modelling
4. Then it is shared with owner and facilitys maintenance operators
Figure 4.1 The traditional and integrated approach to design review.
4.3.12 Planning use of BIM
From the Crusell Bridge project, we learned the following: a comprehensive plan for BIM execution is
needed to get the best value from BIM process. Within the Computer Integrated Construction Research
Program in 2009 the "BIM Project Execution Planning Guide Version 1.0." by the buildingSMART
allianceTM was created. The guide describes four steps for creating the BIM execution plan.
These four steps are the following:
53
1. Identifying high value BIM uses during project planning, design, construction and operational
phases
2. Designing the BIM execution process by creating process maps
3. Defining the BIM deliverables in the form of information exchanges
4