Ehituskorraldus
EHITUSE KÄIGUS
AJUTISED JA ALALISED VÕRGUD VÕIMALUSEL ÜHITADA
2)HOONE MAAPEALSE KARBI EHITUSTÖÖ:
TÖÖFRONT HAARDEALADEKS. KORRUSSEKTSIOON. VÕIMALUSEL
TÖÖ ERVERTIKAALIDEL. 2VAHELAGE
RASKED MATERJALID KORRUSTELE KOOS LAGEDEGA
ENNE ERITÖID SULETAKSE AVAD. TEHAKSE SÜVENDID, VAOD, AUGUD.
KROHVITAKSE NISID
SANTEHNILISED TÖÖD 2s JÄRGUS
* TORUSTIKUD HAARDEALADE KAUPA (sama mis üldehitusel)
SURVETAMINE JA AKT
* KRAANIKAUSID,LOPUTUSKASTID, UNITAAZID jm PEALE
MAALRITÖÖDE 1. ETAPI LÕPPU
ELEKTRITÖÖD 2s JÄRGUS
* TORUD , JUHTMED, KARBID. AKT.
· LÜLITID, PISTIKUPESAD, VALGUSTID PEALE SEINTE
VÄRVIMIST
3) VIIMISTLUSTÖÖD
LÕPETATUD KATUS, SULETUD AKNAD JA UKSED, SANTEHNIKA JA
ELEKTRITÖÖDE 1. JÄRK, MONTEERITUD TÕSTUKID INIMESTE JA
MATERJALIDE VEOKS.
KROHVIMINE JA OLAATIMINE ELAMUS: SANSÕLM- KÖÖK- TOAD
TREPIKODA. EESMÄRK FRONDI AVAMINE
MAALRITÖÖD 2s ETAPIS: