Ehituskorraldus
PROJEKTEERIMIS- EHITUS TÖÖVÕTT - 1 : 4
PEATÖÖVÕTT - 2,5 : 2,5
JUHTIMISTÖÖETTEVÕTT - 4:1
AJAKRITEERIUMI PRIORITEETSUS JA JUHTIMISKOMPETENTSI
PUUDUMINE SUNNIB ÜHA ENAM KASUTAMA
JUHTIMISTÖÖVÕTTU VAATAMATA SUUREMALE RISKILE
3.4. HINNAKUJUNDUSE VIISID
MÕJUTAB OTSESELT RISKI JA TÖÖ JAOTUST POOLTE VAHEL
A. FIKSEERITUD HIND
· SELGUS ENNE YÖÖDE ALUSTAMIST
· TELLIJAL MADAL RISKITASE
· TELLIJA KULUD MAKSUMUSKOTROLLILE ON VÄIKSEIMAD
· EHITUSETTEVÕTJA KASUM AGA KA RISK ON SUURIMAD
B.KULUDE KATMISEL PÕHINEV HIND
· SOOVITAV AVARII JA REMONNITÖÖDE PUHUL
· VÕIMALDAB ALUSTADA TÖID VÄGA VARASES STAADIUMIS
19
· TELLIJA HINNARISK SUUR
· TELLIJA KULUD HINNAKONTROLLILE
· KULUD MIS KUULUVAD TASUMISELE PEAKS OLEMA
LEPINGUS FIKSEERITUD ( TÖÖTASU TARIIFID, ÜLDKULU
ARTIKLID )