Ehituskorraldus
· MASINATE JA INVENTARI VAJADUSE GRAAFIKUD
KALENDERPLAAN TABELI KUJUL - JOONIS 5.25
KALENDERPLAANI AKTUALISEERIMISE VÕTTEID JOONIS 5.26
5.9.EHITUSTÖÖ KORRALDUSE PROJEKTEERIMINE
EESMÄRK :
1) MÄÄRATA TÖÖPLAAN (ETTEKIRJUTUS) RUUMIS JA AJAS
2) MÄÄRATA EHITUSKESTUS
3) MÄÄRATA EHITUSTÖÖ KORRALDUSEGA PLATSIL SEOTUD
KULD
KAKS VIIMAST MÕJUTAVAD LEPINGU HINDA JA PEAVAD OLEMA
MÄÄRATUD ENNE HINNAPAKKUMIST
KALENDERPLAANIDEST JA KOORMUSEPÜÜRIDEST LOETAKSE VÄLJA
KAUD- EHK ÜLDKULUDE MÄÄRAMISEKS JÄRGMISED PARAMEETRID:
· EHITUSE KOGUKESTUS
· ÜKSIKUTE ETAPPIDE KESTUSED
· TÖÖ KESTUS TALVEPERIOODIL
· VEEÄRASTUSAJA KESTUS
· LAOPLATSI JA TÖÖEE VALGUSTUSAJA KESTUS
· TORNKRAANA JATÕSTUKITE TÖÖAJA KESTUS
· TÖÖLISTE KESKMISED JA MAKSIMAALSED ARVUD, MILLEST
OLENEB SOOJAKUTE JA SÖÖKLATE VAJADUS