Ehituskorraldus
EHITUSED ) JA RISKI JAOTUS
3.3.1.KULUD
KÕIGE OLULISEM TEGUR
1) HINNA TASE
2) HINNA KINDLUS
MADALAIMA HINNA ANNAB VÕISTUPAKKUMINE
KESTUS ARVESTATAKSE KITSENDUSENA ( TÄHTAEG )
KVALITEET TAGATAKSE : KORREKTSELT VORMISTATUD
TÖÖMAHTUDE LOENDI JA TÖÖDE KIRJELDUSEGA
( SPETSIFIKATSIOONIDEGA ) PROJEKTEERIMISE FAASIS JA
KAHEETAPILISE VÕISTUPAKKUMISEGA TÖÖETTEVÕTU
KORRALDUSE FAASIS
HINNAKINDLUS PÖÖRDVÕRDELINE HINNARISKIGA
· PROJEKTEERIMIS-EHITUS TÖÖETTEVÕTT FIKSEERITUD
HINNAGA: TELLIJA EHITJA VAHELINE HINNARISKI JAOTUS
1:4
* PEATÖÖETTEVÕTT, RISKIJAOTUS 1:4 , MÄÄRAMATUS
TELLIJA JAOKS PIKEM
· JUHTIMISTÖÖETTEVÕTT , RISKIJAOTUS 4:1. NÕUAB
HINNAKONTROLLI KEHTESTAMIST
MAKSUMUSE HINDAMISE VIGA:
15
· TASUVUSUURINGUD 20-25 %
· INVESTEERIMISOTSUS 15%
· TEHNILINE KAVAND 10%