Ehituskorraldus
VÕISTUPAKKUMISE KORRALDAMINE, EHITUSE JÄRELEVALVE,
TOPOGEODEETILISED UURINGUD JM
ILMA LOETLETUD LISATÖÖDETA MOODUSTAB
PROJEKTEERIMISMAKSUMUS EHITUSE MAKSUMUSEST 5-10%
PROJEKTEERIMISE HIND MÄÄRATAKSE KAS :
· KOGUSUMMANA
34
· % EHITUSMAKSUMUSEST
· KULUDE KATMISEGA KOKKULEPITUD TUNNITARIIFIALUSEL
PROJEKTEERIJA VASTUTUS EHITUSMAKSUMUSE PIIRLIMIIDI ( Q )
ETTESEADMISEL :
· KUI MADALAIM PAKKUMISHIND EHITUSELE ÜLETAB Q
ROHKEM KUI 10% - TASUB ÜMBERPROJEKTEERIMISE
KONSULTANT
· KUI VÄHEM KUI 10% - SIIS TELLIJA
MAKSIMAALSE KONSULTATSIOONITÖÖ PAKETI PUHUL ON
TÖÖMAHUKUSE JAOTUS JÄRGMINE:
* EELKAVAND 15%
* TEHNILINE KAVAND 20%
* PAKKUMISDOKUMENDID 40%
* VÕISTUPAKKUMISE KORRALDUS 5%
* LEPINGU JUHTIMINE JA JÄRELEVALVE 20%